Timeline

Here is my timeline for the project.  I really wish I could import my spreadsheet...anyone know how?












MAY











Set-Up












May 1-7










Clear Kitchen, Built-in, China Cabinets






May 7-10








Demolish Kitchen and Built-in









May 8-10








Remove Baseboards













May 10-11








Empty China Cabinets/Move Furniture







May 9-11








Floor Patching and Refinishing










May 11-14






Arrange for Cabinet Delivery















May 17-18


Plumber



















May 19-20


Electrician Work



















May 20-24
Install Pocket Door




















May 21-26
Cover Floors










May 24-26
 


JUNE








Drywall Repairs/Build/Fix/Restore
June 1-5
Paint
June 6-12
Install Cabinets
June 11-26
Counters - call for measure
June 27-30

 JULY
 
InstallBaseboards
 
 AUGUST
 
CounterInstall
 
Plumber
Backsplash
 
LightFixtures,handles,etc.