Here is my timeline for the project. I really wish I could import my spreadsheet...anyone know how?
|
|
|
|
|
|
|
|
|
|
|
MAY | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
| |
Set-Up |
|
|
|
|
|
|
|
|
|
|
|
|
| |
May 1-7 | |
|
|
|
|
|
|
|
|
|
|
| |
Clear Kitchen, Built-in, China Cabinets |
|
|
|
|
| |
|
|
| May 7-10 |
|
|
|
|
|
|
|
|
| |
Demolish Kitchen and Built-in |
|
|
|
|
|
|
| |
|
|
|
| May 8-10 |
|
|
|
|
|
|
|
|
| |
Remove Baseboards |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
| May 10-11 |
|
|
|
|
|
|
|
|
| |
Empty China Cabinets/Move Furniture |
|
|
|
|
| |
|
|
|
| May 9-11 |
|
|
|
|
|
|
|
|
| |
Floor Patching and Refinishing |
|
|
|
|
|
|
| |
|
|
|
|
| May 11-14 |
|
|
|
|
|
|
| |
Arrange for Cabinet Delivery |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| May 17-18 |
|
|
| |
Plumber |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| May 19-20 |
|
|
| |
Electrician Work |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
| May 20-24 | | |
Install Pocket Door |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| May 21-26 | |
Cover Floors |
|
|
|
|
|
|
|
|
|
|
| |
| | | | | | | | | | | | May 24-26 |
Drywall Repairs/Build/Fix/Restore | | | | | | | | | | | |
June 1-5 | | | | | | | | | | | | | | | | | |
Paint | | | | | | | | | | | | | | | | | | |
| | | | June 6-12 | | | | | | | | | | | | | |
Install Cabinets | | | | | | | | | | | | | | | | |
| | | | | | June 11-26 | | | | | | | | | | | |
Counters - call for measure | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | June 27-30 |
LightFixtures,handles,etc.